FAR 52.232-22 Limitation of Funds

Does the regulation require it to flow down?

No

The prime includes it to avoid exposure between installments: the sub works only up to the limit of what the prime has allotted, and gives notice before touching it

A clause can reach your subcontract without a mandate. Once it is in your document, it is a contract term all the same. The missing mandate is a fact about the regulation. It is not a ruling on your order.

Checked against acquisition.gov on 2026-08-04 · edition APR 1984 · base v0.9.3 Read the text ↗

What it makes you produce

3 items for your checklist, slowest first.

  1. Something you write2

    Days to weeks, and nobody outside your company has to agree to it.

    • Written notice when the cost expected over the next 60 days, added to everything already incurred, will pass 75 percent of the funds allotted so far — a different number from the total estimated cost

      FAR 52.232-22(c)
    • Notice 60 days before the end of the period the Schedule sets, with the estimate of the funds needed to continue

      FAR 52.232-22(d)
  2. Nothing to send now

    It does not hold the order. It decides what money moves later — what you can claim, what can be claimed from you, and what can be held back — and none of that changes after signature.

    • Nothing above the allotted amount is reimbursable, and where no further funds are allotted after the notice, the right to stop work is the protection the clause carries

      FAR 52.232-22(e)

Source: acquisition.gov, FAR 52.232-22 (verified 2026-08-04)

This is research, not legal advice. It states what the regulation says about this clause and cites the paragraph behind it. It does not rule on your order, and it does not rule on whether a prime's markings are correct.