FAR 52.223-7 Notice of Radioactive Materials

Does the regulation require it to flow down?

Yes

(d): in all subcontracts for radioactive materials meeting the criteria in (a)

Form
verbatim ('this clause... shall be inserted'), including (d) itself
Reaches
all tiers

Checked against acquisition.gov on 2026-08-04 · edition JAN 1997 · base v0.9.3 Read the text ↗

What it makes you produce

2 items for your checklist, slowest first.

  1. Something you write2

    Days to weeks, and nobody outside your company has to agree to it.

    • A written notice to the contracting officer describing the part, the isotope, its activity and the manufacturer, the stated number of days before delivery or before servicing is complete

      FAR 52.223-7(a)
    • MIL-STD-129 marking and labels on every item, part or subassembly above the activity criteria, and on the containers they ship in

      FAR 52.223-7(c)

When it is used

Supplies contracts where the item contains radioactive material that requires a license under the Atomic Energy Act or has specific activity above 0.002 microcuries/gram ((a)). The advance-notice period is filled in by the Contracting Officer in the contract (the text leaves the number of days blank). No dollar threshold.

Read closely

The number of days is filled in by the contracting officer, set to leave time for licenses and safety precautions at the receiving end — a blank there is a question rather than a zero. (b) lets a repeat delivery of unchanged material go forward on a written waiver request naming the earlier notice and its contract number. The trigger sits in the bill of materials: sights, dials, smoke detectors and luminous instruments are the usual carriers.

The 15 templates that name it, with the line
76CORPDOC 2A — FAR/DFARS Flowdown Provisions for Commercial Products/Services under a DoD Prime ContractLockheed Martinline 222143CORPDOC 3A — FAR/DFARS Flowdown Provisions for Fixed Price Non-Commercial Items under a DoD Prime ContractLockheed Martinline 193155CORPDOC 4A — FAR/DFARS Flowdown Provisions for Cost-Reimbursement/T&M Subcontracts under a DoD Prime ContractLockheed Martinline 213233RTX Flowdown of U.S. Government Contract Clauses Under U.S. Government ContractsRTXline 86451Raytheon TC-001 — General Terms and Conditions of PurchaseRTXline 489105Raytheon TC-002 — Supplement 1: Government Contract Provisions from the FARRTXline 70166Northrop Grumman CTM-P-ST-001 — U.S. Government Firm Fixed Price Order (Not for Commercial Products and Services)Northrop Grummanline 2288166Northrop Grumman CTM-P-ST-003 — U.S. Government T&M Order (Not for Commercial Products and Services)Northrop Grummanline 2230168Northrop Grumman CTM-P-ST-004 — U.S. Government Cost Reimbursement Order (Not for Commercial Products and Services)Northrop Grummanline 2328255GD Mission Systems SCM-TMP-005 — General Provisions, Firm Fixed Price PO under U.S. Government Contract (Non-Commercial)General Dynamicsline 1043243GD Mission Systems SCM-TMP-048 — T&M Purchase Orders for Non-Commercial Items in Support of a U.S. Government ContractGeneral Dynamicsline 1964122GD Mission Systems SCM-TMP-095 — FFP Purchase Orders for Commercial/COTS Products or Services in Support of a U.S. Government ContractGeneral Dynamicsline 1015240L3Harris LGL-50.F1 — General T&C and Flowdown Clauses for Other Than Commercial Products/Services under a U.S. Government ContractL3Harrisline 1751273BAE Systems Inc. USGOVA — FAR/DFARS Flow Down Provisions for Subcontracts/Purchase Orders under a U.S. Government (DoD) Prime ContractBAE Systemsline 344178AAR Component Services NY — U.S. Government Contract FAR and DFARS Clauses Incorporated by ReferenceAAR Corpline 801

Source: acquisition.gov, FAR 52.223-7 (verified 2026-08-04)

This is research, not legal advice. It states what the regulation says about this clause and cites the paragraph behind it. It does not rule on your order, and it does not rule on whether a prime's markings are correct.