No
No flow-down paragraph in the text (verified); the prime includes it in every cost-type subcontract because it needs the sub's costs to be allowable under FAR 31 and to close the voucher and final-rates cycle — without it, the sub's cost becomes disallowance risk in the prime's own audit
A clause can reach your subcontract without a mandate. Once it is in your document, it is a contract term all the same. The missing mandate is a fact about the regulation. It is not a ruling on your order.
Checked against acquisition.gov on 2026-08-04 · edition AUG 2018 (Basic; Alt I FEB 1997, Alt II–IV AUG 2012) · base v0.9.3 Read the text ↗
What it makes you produce
2 items for your checklist, slowest first.
Something you write
Days to weeks, and nobody outside your company has to agree to it.
An adequate final indirect cost rate proposal within the six months following the expiration of each of your fiscal years
FAR 52.216-7(d)(2)(i)
Something you fill in and send back
Hours, once you know which one is missing.
Interim vouchers billed against incurred cost
FAR 52.216-7(a)
When it is used
Enters every cost-reimbursement contract (prescribed at 16.307(a)), with no dollar threshold. Flows down when the prime issues a cost-type subcontract — not by FAR mandate, but because the prime can only bill the government for sub costs that follow the same allowability rules and the same final-rates cycle.
Read closely
No paragraph of this clause asks for an accounting system. What it asks for is the proposal at (d)(2)(i); the schedules listed at (d)(2)(iii) — claimed rates, pools and bases, expenses by cost element, direct and indirect cost by contract and subcontract, and a reconciliation to your accounting records — are drawn out of the books you already keep. Missing the six-month deadline is the standard failure for a small company on cost-type work, and paragraph (g) is the audit right behind all of it.
The 11 templates that name it, with the line
Source: acquisition.gov, FAR 52.216-7 and 16.307(a) (verified 2026-08-04)
This is research, not legal advice. It states what the regulation says about this clause and cites the paragraph behind it. It does not rule on your order, and it does not rule on whether a prime's markings are correct.